|
| Products | ||||
| A | B | C | Total | |
| Sales and production (units) | 90,000 | 30,000 | 15,000 | 135,000 |
| Raw materials usage (units) | 10 | 7 | 14 | 1,320,000 |
| Direct materials cost (£) | 30 | 40 | 15 | 4,125,000 |
| Direct labour hours | 2.5 | 3 | 1.5 | 337,500 |
| Machine hours | 5 | 3 | 7.5 | 652,500 |
| Direct labour cost (£) | 20 | 30 | 10 | 2,850,000 |
| Number of production runs | 5 | 10 | 50 | 65 |
| Number of deliveries | 18 | 7 | 50 | 75 |
| Number of receipts | 50 | 70 | 700 | 820 |
| Number of production orders | 45 | 25 | 60 | 130 |
| Overhead costs | £ |
| Set up | 75,000 |
| Machines | 1,000,000 |
| Receiving | 900,000 |
| Packing | 650,000 |
| Engineering | 750,000 |
| Total | 3,375,000 |
Traditional direct labour hours basis
The direct labour hour rate is £10, calculated by dividing the total overheads by the total number of direct labour hours:
| total overheads |
| total number of direct labour hours |
| 3,375,000 |
| 337,500 |
| £10 per dlh |
Since we are using the direct labour hour rate method for the absorption of all overheads, the product costs per unit must be:
| A | B | C | |
| Direct Materials | 30 | 40 | 15 |
| Direct Labour | 20 | 30 | 10 |
| Overheads | 30 | 15 | 15 |
| Total Product Cost | 25 | 30 | 40 |
Direct labour hour rate x number of direct labour hours per product
For product A, for example, the calculation is:
£10 per dlh x 2.5 dlh = £25
Multiple volume based allocation method
The multiple volume allocation method is an advance on the traditional allocation method in that it does make some allowance for activities to influence the absorption of overheads. In this example, we have two absorption rates to apply here: the receiving department overhead rate, and the "other" overhead rate
The reasoning here is that the organisation we are simulating is using a two rate basis of apportioning overheads: firstly, a material handling overhead rate is used to assign overhead to a separate cost centre and then charge it to production on the basis of the number of receipts; secondly all of the other overheads are assigned using a general machine hour rate on the basis that the number of machine hours far exceeds the number of labour hours.
Notice here, the rate we are using to assign the materials handling overheads is based on the number of receipts of materials into a department. The reason we are using this rate is that the activity of receiving dominates the reason for the existence of the overhead. Drury uses an overhead rate expressed as a percentage of direct materials cost. This is not a rate to be recommended particularly since tying the assignment of an overhead to the cost of a material is not realistic. As we know, merely because a material is expensive does not mean that its attendant overheads will vary in proportion to it.
The receiving overhead rate is
| Total receiving overheads |
| Total number of receipts |
| £900,000 |
| 820 |
| £1,097.56 per receipt |
Using this rate as a constant allows us to evaluate the product overhead
apportionments:
overheads per receipt x receipts per product group
For product A:
£1,097.56 per receipt x 50 receipts
£54,878
| Product | |||
| A | B | C | |
| Receiving overheads apportionment | £54,787.0 | £76,829.3 | £768,292.7 |
| Product | |||
| A | B | C | |
| Receiving cost per unit | £0.60976 | £2.5610 | £51.2195 |
Overhead absorption rate:
£900,000 x 100 = 21.82%
= £4,125,000
Applying this rate to each product's material costs gives:
| Product | ||
| A | B | C |
| £6.55 | 8.73 | 3.27 |
| £3,375,000 900,000 | = £3.79103 |
| 652,000 machine hours |
When multiplied by the number of machine hours per product, this then gives us
the cost per unit for other overheads. For example, in the case of product A,
the calculation is:
£3.79103 x 5 machine hours per unit = £18.9655
Once all the calculations have been completed, the product cost analysis per
unit of each product is:
| Product | |||
| A | B | C | |
| Direct materials | 30.0000 | 40.0000 | 15.0000 |
| Direct labour | 20.0000 | 30.0000 | 10.0000 |
| Materials overheads | 0.6098 | 2.5610 | 51.2195 |
| Other overheads | 18.9655 | 11.3793 | 28.4483 |
| Total Product cost | £69.5753 | 83.9403 | 104.6678 |
As we said above, to apply the ABC method, we need to identify cost drivers for two stages:
1 cost drivers tracing the costs of inputs into cost pools; and
2 cost drivers tracing the cost pools into product costs
The workings that follow illustrate clearly how such cost drivers work through the ABC system in these two stages: an initial overhead rate or amount being further subdivided according the needs of the situation.
workings:
The calculations for each of the rates to be used are:
The machine hour rate is the only rate that is what we might call a traditional rate. All of the other rates we are about to use involve a two stage process. We will see the elements of these two stages as we get to them.
machine hour overhead rate
| £1,000,000 | = £1.5326 |
| 652,500 machine hours |
This rate is used as normal.
For the set up costs, we first devise a rate to tell us the cost per set up: total set up overheads divided by the number of set ups: in this case, this is
| £75,000 | = £1,153.85 |
| 65 production runs |
We will return to this rate shortly.
All of the other rates are calculated similarly. Hence they will be presented now without further comment.
| Receiving rate | £900,000 | = £1,097.56 |
| 820 receipts |
| Packing rate | £650,000 | = £8,666.67 |
| 75 deliveries |
| Engineering rate | £750,000 | = £5,769.23 |
| 130 production orders |
All of this information can now be put together into a cost per unit statement as follows.
The final stage in the whole ABC procedure, as far as product cost determination is concerned is to find out the costs per unit. The cost per unit statement follows, and then we will work through the calculations.
| Unit costs | A | B | C |
| £ | £ | £ | |
| Direct materials | 30.0000 | 40.0000 | 15.000 |
| Direct labour | 20.000 | 30.000 | 10.000 |
| Machine overheads | 7.6628 | 4.5977 | 11.4943 |
| Set up costs | 0.0641 | 0.3846 | 3.8462 |
| Receiving costs | 0.6098 | 2.5610 | 51.2195 |
| Packing costs | 1.7333 | 2.0222 | 28.8889 |
| Engineering costs | 2.8846 | 4.8077 | 23.0769 |
| Total Costs | £62.9546 | £84.3732 | £143.5257 |
workings:
Machine overheads are found by multiplying the machine hour rate by the number of machine hours per product per unit:
machine hour rate £1.5326 x
| machine hours | 5 | 3 | 7.5 |
| gives | £7.6628 | 4.5977 | 11.4943 |
Set up cost per set up £1153.85 x
| No of set ups | 5 | 10 | 50 |
| gives | £0.0010 | 0.0059 | 0.0592 |
| No of set ups | 5 | 10 | 50 |
| gives | £5,769.25 | 11,538.50 | 57,692.50 |
| £0.0641 | 0.3846 | 3.8462 |
| Product | |||
| A | B | C | |
| DLH | 75.0000 | 100.0000 | 40.0000 |
| Mult | 69.5753 | 83.9403 | 104.6678 |
| ABC | 62.9546 | 84.3732 | 143.5257 |
| Product | |||
| A | B | C | |
| DLH | 25.0000 | 30.0000 | 15.0000 |
| Mult | 19.5753 | 13.9403 | 79.6678 |
| ABC | 12.9546 | 14.3732 | 118.5257 |
| Product | |||
| A | B | C | |
| DLH | 33.33% | 30.00% | 37.50% |
| Mult | 28.14% | 16.61% | 76.11% |
| ABC | 20.58% | 17.04% | 82.58% |
© Duncan Williamson